(a) To recover in a suit under Section 2253.073 on a payment bond for a claim for payment for public work labor performed or public work material delivered, a payment bond beneficiary must mail to the prime contractor and the surety written notice of the claim.
(b) The notice must be mailed on or before the 15th day of the third month after each month in which any of the claimed labor was performed or any of the claimed material was delivered.
(c) The notice must be accompanied by a sworn statement of account that states in substance: (1) the amount claimed is just and correct; and (2) all just and lawful offsets, payments, and credits known to the affiant have been allowed.
(d) The statement of account shall include the amount of any retainage applicable to the account that has not become due under the terms of the public work contract between the payment bond beneficiary and the prime contractor or between the payment bond beneficiary and a subcontractor.
(a) Except as provided by Section 2253.044, if a written agreement does not exist between the payment bond beneficiary and the prime contractor or between the payment bond beneficiary and the subcontractor, the notice for a claim for unpaid bills must contain: (1) the name of the party for whom the public work labor was performed or to whom the public work material was delivered; (2) the approximate date of performance or delivery; (3) a description of the public work labor or material for reasonable identification; and (4) the amount due.
(b) The payment bond beneficiary must generally itemize the claim and include with it copies of documents, invoices, or orders that reasonably identify: (1) the public work labor performed or public work material delivered for which the claim is made; (2) the job; and (3) the destination of delivery.
The notice for a claim for lump-sum payment for multiple items of public work labor or material must:
(1) describe the labor or material in a manner that reasonably identifies the labor or material;
(2) state the name of the party for whom the labor was performed or to whom the material was delivered;
(3) state the approximate date of performance or delivery;
(4) state whether the contract is written or oral;
(5) state the amount of the contract; and
(6) state the amount claimed.
The notice for a claim for public work labor performed or public work material delivered by a payment bond beneficiary who is a subcontractor or materialman to the prime contractor or to a subcontractor and who has a written unit price agreement that is wholly or partially completed is sufficient if the beneficiary attaches to the sworn statement of account:
(1) a list of units and unit prices set by the contract; and
(2) a statement of those completed and partially completed units.
(a) To recover in a suit under Section 2253.073 on a payment bond for a claim for payment of retainage, a payment bond beneficiary whose contract with a prime contractor or subcontractor provides for retainage must mail written notice of the claim to the prime contractor and the surety on or before the 90th day after the date of final completion of the public work contract.
(b) The notice shall consist of a statement of: (1) the amount of the contract; (2) any amount paid; and (3) the outstanding balance.
(c) Notice of a claim for payment of retainage is not required if the amount claimed is part of a prior claim made under this subchapter.
(a) To recover in a suit under Section 2253.073 on a payment bond, a payment bond beneficiary who does not have a direct contractual relationship with the prime contractor for public work labor or material must mail notice as required by this section.
(b) A payment bond beneficiary who contracts with a subcontractor for retainage must mail, on or before the 15th day of the second month after the date of the beginning of the delivery of public work material or the performance of public work labor, written notice to the prime contractor that: (1) the contract provides for retainage; and (2) generally indicates the nature of the retainage.
(c) The payment bond beneficiary must mail to the prime contractor written notice of a claim for any unpaid public work labor performed or public work material delivered. The notice must be mailed on or before the 15th day of the second month after each month in which the labor was performed or the material was delivered. A copy of the statement sent to a subcontractor is sufficient as notice under this subsection.
(d) The payment bond beneficiary must mail to the prime contractor, on or before the 15th day of the second month after the receipt and acceptance of an order for specially fabricated material, written notice that the order has been received and accepted.
(e) This section applies only to a payment bond beneficiary who is not an individual mechanic or laborer and who makes a claim for wages.
(a) A notice required by this subchapter to be mailed must be sent by certified or registered mail.
(b) A notice required by this subchapter to be mailed to a prime contractor must be addressed to the prime contractor at the contractor's residence or last known business address.
(c) A person satisfies the requirements of this subchapter relating to providing notice to the surety if the person mails the notice by certified or registered mail to the surety: (1) at the address stated on the bond or on an attachment to the bond; (2) at the address on file with the Texas Department of Insurance; or (3) at any other address allowed by law.